The Brief:

The Environment Agency required the bearings on a 28-tonne radial sluice gate at Porters Lock to be replaced as part of planned infrastructure maintenance. The work had to be carried out in situ, meaning the sluice could not be removed from the structure. To access and replace the bearings safely, the gate needed to be lifted and supported while the existing components were removed and new bearings installed.

The project also had to be carefully timed around the Environment Agency’s river draw-down schedule. This meant the work window was limited and required precise planning to ensure the equipment, steelwork and installation team were ready to complete the task safely within the available timeframe.

“All work was coordinated around the Environment Agency’s scheduled river draw-down to ensure safe access and efficient delivery of the bearing replacement.”

The Solution:

Hotchkiss Westwell designed, manufactured and installed a temporary sluice support structure engineered to BS EN 1090-1 EXC2 standards. This bespoke steelwork allowed the 28-tonne sluice gate to be lifted using hydraulic jacks, taking the load off the existing bearings so they could be removed and replaced without dismantling the entire gate assembly.

Once the sluice had been safely raised, the existing bearings and housings were removed and replaced with new SKF Cooper split bearings and housings supplied by Hotchkiss Westwell. Using split bearings allowed the team to carry out the replacement efficiently while keeping disruption to the structure to a minimum.

After installation and testing of the new components, the sluice gate was carefully lowered back into position and returned to service. The temporary support steelwork was then removed and stored so it can be reused for future maintenance operations.

The project was completed within six months from receiving the order to final completion, with all work coordinated around the Environment Agency’s scheduled river draw-down to ensure safe access and efficient delivery of the bearing replacement.

Leave a Reply